PRESENTATION OF MONTAGI EAD – SOFIA – Branch PERNIK

MONTAGI EAD – SOFIA – Branch PERNIK has the following field of activity:Production, engineering and commercial activity in Bulgaria, construction, assembly, manufacturing of commodities and articles, and any other legal activity.

The Branch is in a position to offer its partners design, supply, make up, assembly, adjustment and putting into operation of:

  • Technological equipment
  • Steel structures
  • Lifting and transporting facilities
  • All kind of electric installations, power supplies and sub-stations
  • Instrumentation for measuring, control and automation
  • Industrial pipelines
  • Welding and weld testing works
  • Furnace construction, insulation and anti-corrosion works
  • HVAC installations
  • Ventilation and heating installations
  • Tanks and tank storages
  • Manufacturing of elements, structures and details

The Branch, in its up to date activity has implemented works in assembly, expansion, reconstruction and modernization of projects in the sector of metallurgy, machine engineering, building industry, chemical and petrochemical industry, food industry, electronics, cement and paper industry.

In carrying out its construction and assembly activity, the branch has available state-of-the-art tools and facilities, production teams, storage facility and elements workshop.

Applying of the latest and modern technologies in the assembly works ensures high quality in compliance with the requirements of international quality standards.

Technical management of projects is done by staff of engineers and technicians, who have been certified by the State Inspection of Technical Supervision, as the staff is preparing the required technical documentation in accordance with the laws in Bulgaria.

In carrying out its activities, MONTAGI EAD – SOFIA – Branch PERNIK has technical management of 14 persons.

  • Machine engineers - 6 persons
  • Electrical engineers - 4 persons
  • Machine technicians - 3 persons
  • Electricians - 1 person

Operating staff of 126 persons as follows:

  • Machine fitters  - 46 persons
  • Welders  - 12 persons certified by TÜV
  • Electric fitters - 43 persons
  • Drivers - 5 persons
  • Auto crane operators - 2 persons
  • BK-300 crane operator  - 1 person
  • Surveyor - 1 person

L I S T of major projects completed and in progres - last 5 years

Investor

Name of Project and Kind of Works

Location

Completed in

1

Municipality of Sofia

"Kubratovo" Water treatment plant- Erection of process and electrical equipment and installations

Sofia

2000

2

Municipality of Sofia

"Kubratovo" Water treatment plant- Erection of process and electrical equipment and installations

Sofia

2000

3

Agrovodinvest - Sofia

"Kurilo" - Pump station - Reconstruction and modernization

Sofia

2001

4

Municipality of Sofia

Metroplitain - Sofia - Erection of process and electrical equipment and installations - Metroststion 2 up to 7

Sofia

2000

5

Municipality of Sofia

Metroplitain - Sofia - Erection of process and electrical equipment and installations- Metrostation "Obelya"

Sofia

2002

6

Granitoid Co. - Batanovtsi

Repair works on mechanical and electrical equipment and installation

Batanovtsi, Pernik region

2001

7

Kremikovtsi Co. - Sofia

Repair works on mechanical and electrical equipment and installation

Metalurgical Works Kremikovtsi - Sofia region

2001

8

INOS-1

"CUM"- Central Universal Market- Sofia - Repairing of roof construc-tion

Sofia

2001

9

Glavbolgarstroy

ECUVD - Airport - Sofia - Erection of electrical equipment and installations

Sofia

2001

10

UMPC - Pirdop

UMPC - Pirdop - Erection of process and electrical equipment and installations

Pirdop

2001

11

UMPC - Pirdop

UMPC - Pirdop - Erection of process and electrical equipment and installations

Pirdop

2002

12

BDZ - Bulgarian rail administra-tion

Electrification of Railway Dupnitsa - Kulata - Erection of electrical equipment and installations

Dupnitsa - Kulata

2001

13

POLIHROM POAP Co.- Sofia

POLIHROM POAP Co.- Erection of process and electrical equipment and installations

Sofia

2001

14

"HILTON - Hotel"- Sofia

HILTON - Hotel - Erection of electrical equipment and installations

Sofia

2001

15

"Toploficatia Sofia"Co.- Sofia

TR"Zemlyane" - Repair works on mechanical and electrical equipment and installation

Sofia

2001

16

KCM-Plovdiv

KCM-Plovdiv - Erection of industrial piping and electrical equipment and installations

Plovdiv

2002

17

Municipality of Sofia

OF"MARKETS" - Erection of new steel structure building of market "Vazrajdane"

Sofia

2002

18

"ELECTROSNABDYA-VANE SOFIA-OKRAG"

Moving the metering panels to a ownship margins.

Sofia region

2002

19

"Flat glass manufacture" - Sofia

"Flat glass manufacture" - Erection of new steel structure building, mechanical and electrical equipment and installations

Sofia

2004

20

Port Burgas

Port Burgas - Erection of new coal terminal - mechanical and electrical equipment and installations

Bourgas

2004-2005

21

"Yastrebets"Hotel-Borovetc

"Yastrebets"Hftel - Erection of new roof steel structure.

Borovetc

2005

22

New USA еmbassy

New USA еmbassy - Sofia - Erection of electrical, clima аnd heating equipment and installations

Sofia

2004-2005

23

"Sofia Med Co" - Sofia

"Sofia Med Co" - Sofia - Erection and reconstruction of mechanical and electrical equipment and installations

Sofia

2003-2005

24

Nuclear Power Station -"Kozloduy"

Repair works on mechanical and electrical equipment and installation

Kozloduy

2003-2005

25

"Mall of Sofia" - Sofia

"Mall of Sofia" - Sofia - Erection of electrical, clima аnd heating equipment and installations

Sofia

2004-2005